Deconstruction of the EDF thermal power station - AMBES - 2011 - 2012


Demolition of 4 chimneys 140 m high and ancillary structures

The works to be deconstructed are:

- 4 chimneys of 147m
- 10 fans; ducts and gantries
- 3 boilers, Oil racks and associated piping
- 4 measurement rooms with metal frames and access stairs
- 1 neutralization pit
- 1 room "fire pumps"
- 4 smoke ducts between chimneys and heaters
- Cleaning, Asbestos Removal (formerly 1513), Dedusting and Decontamination of Processes
- Cleaning, depollution, dust removal and backfilling of technical gutters