Dismantling / Industrial

Auros - GRT Gaz - Dismantling of a Compressor Station


Deconstruction of a Natural Gas Compression Station on behalf of GRT GAZ on the Auros site (33)

- Asbestos removal from roofs and facades

- Decontamination of the process

- Dismantling of processes:
° 1,500 tonnes of scrap
° 3,000 tonnes of concrete
° 5 Compressors
° 1 Water tower 30 meters high
° 1 Electrical substation

- Depollution of soil contaminated with hydrocarbons: 280 m3